Guide · Site visits and photos

Construction daily report: what a superintendent records each day, with photos, and a template to copy

By Blink Brief · Updated  · How pages are made

Record the date and the weather, who was on site by trade and headcount, what work was done and where, deliveries and equipment, inspections and visitors, delays and their cause, safety events, and photos of progress and problems. Write it the same day, in the same order every day: it is the record you go back to when a delay, a change or a dispute comes up weeks later. Copy the layout below into Word, Excel or Google Sheets, and make the photo part on your phone with the free Inspection Report tool.

What goes in a daily report

Construction apps agree on most of the list. Fieldwire's default Daily Report form has weather, schedule delays, weather impact, accidents, injuries, a work log, an equipment log, material deliveries, an activity log, photos and a signature. Raken's daily report has work logs, notes, photos and a survey where delays go. Buildertrend's Daily Logs name site attendance, delays, safety, photos, completed work, site conditions, and materials and equipment. In plain terms:

  • Header: project name and number, site address, report number, date, working hours, and who wrote it.
  • Weather: conditions and temperature in the morning, at midday and at the end of the day, and rain, wind or heat that stopped or slowed any work.
  • Crew on site: each company or trade, how many workers, how many hours, including a sub that was scheduled and didn't come.
  • Work done: what each crew did and where, in the words of the drawings (level, area, gridline), with how far along it is.
  • Deliveries and equipment: what arrived, how much, the ticket number, and what equipment ran and for how long.
  • Inspections and visitors: who came, why, and the result: a passed inspection, a correction notice, an owner's request.
  • Delays: what held work up, which trade, for how long, the cause, and who you told.
  • Safety: the toolbox talk and who attended, incidents and near misses, and "none" when there were none.
  • Photos: numbered, each with a caption and where it was taken.
  • Sign-off: your name, the date and your signature. Fieldwire's help, for one, says its daily reports "must be signed before they are submitted".

A layout to copy (Word, Excel or Google Sheets)

Five tables, in this order. Set them up once in a document or a sheet, fill in what doesn't change (project, address, your name), save it as your template, and start each day from a copy. Keep the order the same every day, so anyone looking for the deliveries on March 12 finds them in the same place.

1. Header

FieldExample
Project and numberRiverside Clinic extension, 24-118
Site address300 Mill Road
Report number and dateDR-047, Friday, November 6, 2026
Working hours7:00 am to 3:30 pm
Weather7 am clear, 41°F; noon 55°F; light rain from 2:15 pm
Written byName, company, superintendent

2. Crew and work

Company or tradeWorkersHoursWork done and where
Own crew, carpenters48Level 2 wall framing, gridlines C to F, about 60% done
Electrical sub28Level 1 rough-in, rooms 104 to 110
Plumbing sub00Scheduled, didn't come; see delays

3. Deliveries, equipment, inspections and visitors

TypeWhat or whoDetail
Delivery2×6 studs, 1 bundle, ticket 55812Stored under cover in the east lot; photo 4
EquipmentTelehandler6 hours
InspectionCity inspector, Level 1 framingPassed; the signed card in photo 6
VisitorOwner's representativeWeekly walk; asked for a sample of the stair finish

4. Delays

What happenedWho it held upTime lostCauseWho you told, when
Plumbing crew didn't comeLevel 1 walls can't be closed1 day for that tradeSub's schedulingSub and PM by email, 8:00 am
Rain from 2:15 pmExterior sheathing1 hour 15 minutesWeatherPM by text, 2:20 pm

5. Safety and photos

#EntryWhere
SafetyToolbox talk on ladder use, 6 attended. No incidents, no near misses.Site office
Photo 1Level 2 framing, looking northLevel 2, gridline C
Photo 4Stud delivery with its ticketEast lot
Photo 6Signed inspection cardLevel 1, room 104

End with your name, the date and your signature. In Word, a photo can go in the photos table under its caption; how to make a photo report in Word has the steps and how to keep the file small enough to email.

Photos: progress, problems, deliveries

  • Progress from the same spots. Pick a few places, such as each corner of the building or each level's stair landing, and take the same view every day. A week of them shows what moved.
  • Problems wide, then close. A wide photo that shows where, then a close one that shows what, with a tape or a hand for scale.
  • Deliveries with their ticket. The material and the delivery ticket in one photo, or two photos numbered together.
  • Before it's covered. Work that the next trade will close up (in-wall plumbing, rebar before a pour, blocking before drywall) is worth a photo the day it's done.
  • Numbers and captions. Photo 4 belongs to the line that says "photo 4". A caption says what and where, not "IMG_4411".
  • The date. Keep the original files, which carry the date the camera recorded; see how to see when a photo was taken. To print the date on the picture itself, Photo Timestamp stamps it on a copy in your browser.

Delays and why they matter later

Delays are the part of a daily report people come back to: when the schedule slips, when a change order is priced, when two parties disagree about who held up whom. A line written that evening by someone who was there is easier to rely on than anyone's memory a month later.

  • Write every delay the same day, even a short one: what happened, which trade or area it held up, from when to when, and the cause as you saw it.
  • Say who you told and how: "PM by email, 8:00 am". Add the photo that shows it, such as the empty work area or the rain on the deck.
  • Facts, not blame. "Plumbing crew didn't come; their office said the van broke down" rather than "plumber unreliable again".
  • Weather with times. "Light rain from 2:15 pm, sheathing stopped at 2:20 pm" says more than "rain".
  • Check your contract. It says how and by when a delay must be reported to the owner. The daily report records the delay; it doesn't replace a notice the contract asks for.

On the phone at the end of the day: a photo report as a PDF

The photos are the part a spreadsheet handles worst. The free Inspection Report tool turns them into a PDF in your phone's browser, with no sign-up, before you leave the site. It is an inspection report: items, each with a photo, a status and a note. Use it for the photos and put the rest of the day in the summary:

  1. Under Report details, add your company name and logo, the Client, the Site address and your name as Inspector, and change Report title to "Daily Report DR-047". Date of inspection starts at today.
  2. Under Items you checked, add one item per photo: the place and the subject in What did you check? ("Level 2 framing, gridline C"), Take photo or Choose photo, a Status, and in Note what the photo shows. Use OK for work on track, Needs attention for a problem or a delay, and Fail for work that was rejected or stopped.
  3. Under Summary and next steps, write the weather, the crews and their headcounts, deliveries, visitors, delays and tomorrow's plan. The summary counts the OK, Needs attention and Fail items for you.
  4. The signature box is labelled for the client. If the owner's representative walked the site with you, they can sign it with a finger; otherwise leave it empty.
  5. Choose US Letter or A4, tap Download PDF, and email it from your phone.

What it doesn't do: it has no weather, crew, delivery or delay tables, only the items and the summary; each item takes one photo; and it keeps nothing after you close the tab, so download the PDF first. Photos are turned upright and reduced to at most 1600 pixels on your device and never uploaded; the page loads its PDF library from cdnjs, and each page of the PDF has a "Made with Blink Brief" line. For a walk with the owner rather than an end-of-day report, see the site visit report template, and for the end of a job, a punch list with photos.

Several jobs, several supers

Once a company runs more than one job, the reports are only useful if every superintendent writes the same one. Give everyone the same template, the same order and the same file names (project number, "Daily Report", date), and agree who gets it and by what time. Number the reports per project, so a missing day shows.

Daily report apps keep that for you, at a price per user. On their pricing pages on 6 November 2026: Raken's Basic plan, with "Branded daily reports" and photos, costs $69 a month for its 3-user minimum, billed annually. Fieldwire's Basic plan is free for up to 5 users, but its Daily Report form, with weather filled in and a signature, needs Business at $64 per user a month, billed annually. CompanyCam has daily logs on every plan, from $63 a month billed annually for one user. CompanyCam alternatives compares them for 1 user and a crew of 3, and inspection report apps compared covers report apps.

The free tool can't keep a template or put several supers under one company: each person types the report details again every day.

Our product · in development

Blink Inspection Report: set up your checklist once and every report starts from it. Everyone on your team writes reports under your company name, and when the client signs on your screen, the PDF goes to their email address without you attaching anything. It makes inspection reports (items with photos and a status), not a full daily log with crew and weather fields. Planned price $29 a month; reserving a place costs $29, the first month.

Join the early list

Questions

What should a construction daily report include?

The project, the date and the report number; the weather; each company or trade on site with its headcount and hours; the work done and where; deliveries and equipment; inspections and visitors; delays with their cause and who you told; safety events and the toolbox talk; numbered photos with captions; and your name and signature. Fieldwire's default Daily Report form, Raken's daily report and Buildertrend's Daily Logs each name most of these parts.

Who writes the daily report on a construction site?

The superintendent or the foreman who ran the work that day, for the project manager, the owner or the file. On a job with subcontractors, each sub's foreman may write one for their own crew; Raken, for one, combines a general contractor's report with the subcontractors' reports for the day into a single PDF it calls the Super daily report.

How do you write a good daily report?

Write it the same day, in the same order every day, and keep to facts: headcounts, hours and quantities as numbers, places in the words of the drawings (level, room, gridline), the times a delay started and ended and who you told, and a numbered photo for each thing you mention. Leave opinions and blame out.

Is there a free construction daily report app?

Not a full one among the daily report apps read on 6 November 2026. Fieldwire's Basic plan is free for up to 5 users and 3 projects, but its Daily Report form needs the Business plan ($64 per user a month, billed annually). Raken starts at $69 a month for its 3-user minimum, billed annually, and CompanyCam has daily logs on every plan but no free plan. Free routes: the layout on this page in a spreadsheet, and the free Inspection Report tool for the day's photos as a PDF.